You must give us notice before carrying out a demolition.
Demolition notice
You must not start work to demolish a building until either you receive notice from the council or six weeks have elapsed. This is a requirement of the Building Act 1984 (legislation.gov.uk).
You do not need to give notice when demolishing a building smaller than 1,750 cubic feet in volume.
Download a demolition notice form
Fees are listed in our schedule of supplementary charges.
Read more about demolishing a building on the Planning Portal website.
Contact us
To contact the Building Control team, telephone 020 8583 5454 or email buildingcontrol@hounslow.gov.uk.
Skip permits
If you need to place a skip on the road, read our guidance on how to apply for a skip licence.